Sigenergy Shut down and Restart Guide
Step by Step Guide
Before You Start
- Perform the restart during daylight hours if your system includes PV input
- Make sure there are no active backup loads running before shutdown
- Do not restart during a firmware update or while the system is in backup mode
- Never restart during a lightning storm or when system components appear damaged
1. Turn off the AC isolator
This switch is located inside the Sigenergy Gateway.
- Find the switch labelled Inverter Supply and flip it to OFF to stop the AC power supply to the inverter
2. Turn off the DC isolator
The DC switch is located inside the small cover on the left-hand side of the inverter.
- Remove the cover by lifting it upwards and away from the inverter
- Turn the switch labelled DC to the OFF position
3. Wait 1–2 minutes
Allow all lights and display indicators to switch off completely.
- This ensures internal capacitors discharge and the system resets fully
4. Turn the DC isolator back ON
Switch the DC isolator to ON and wait approximately 5 seconds before continuing.
5. Turn the AC isolator back ON
Switch the AC isolator back to ON.
6. Allow the unit to start up
The unit will run internal checks and initialise communication.
- Within a few minutes, the inverter display or LEDs should show normal operation
7. Verify operation
Check the LED indicators — the green AC, DC and Battery LEDs should be lit with no fault or alarm codes.
- Open the mySigen app to confirm that power generation and communication data are updating normally
- If a warning or fault reappears after restart, note the fault code before contacting your installer or Sigenergy support